Cat A fit-out
- Guide cost, central London
- £650 to £1,020 per m²
- Regional cities
- £490 to £820 per m²
- Typical programme
- 8 to 16 weeks per floor plate
Category A is the finish a landlord delivers to make a floor lettable: a clean, lit, heated and cooled open space with working toilets, ready for a tenant to add their own layout. It sits between shell and core (the bare building) and Category B (the occupier's fit-out).
There is no statutory definition. The industry reference is the British Council for Offices Guide to Specification, and most landlords and agents describe Cat A against it.
What Cat A normally includes
- Floors and ceilings
- Raised access floor for cabling and a suspended ceiling, or an exposed soffit finished to a good standard.
- Lighting and power
- LED lighting to an open-plan layout with controls, and power to the floor boxes, but not to individual desks.
- Heating, cooling and ventilation
- Air conditioning and fresh air sized for open-plan occupancy, commonly fan coil units or VRF, with a building management system.
- Fire, toilets and core
- Fire alarm and sprinklers where fitted, finished toilets and showers, lift lobbies and stairs decorated, blinds to windows.
Schedule of rates, Cat A and around it
| Item | Scope | Guide cost |
|---|---|---|
| Cat A fit-out | Ceilings, raised floor, lighting, heating and cooling to open plan, toilets and core finishes | £650 to £1,020 per m² |
| Cat A "plus" | Cat A with some meeting rooms and a kitchen built speculatively | £1,020 to £1,510 per m² |
| Standard Cat A reinstatement | Removing a tenant's Cat B and putting the floor back to Cat A | £320 to £590 per m² |
| Cat B on top of Cat A | Partitions, meeting rooms, tea points, finishes and services moved to suit the layout | £1,300 to £2,150 per m² |
Central London rates per m² of net internal area, Q1 2026 published guides, before VAT and fees. Cat A "plus" converted from £95 to £140 per ft². A guide, not a quote. Build a budget in the cost plan.
Getting Cat A right
Shell and core, Cat A, Cat B
Shell and core is the structure, facade, lifts, stairs, toilets in the core and main plant, with the office floors left bare. Cat A adds the finishes and services that make a floor usable by anyone. Cat B is everything that makes it usable by one particular tenant. The line between Cat A and Cat B varies from building to building, so the specification, not the label, decides what is in the price.
Design it for the occupancy you expect
Cooling, fresh air and the number of toilets are sized for a density. The BCO's 2023 guide moved its recommended design density for speculative offices from 8 m² to 10 m² per person, reduced the small power allowance per person, and asks for more outdoor air than before. A Cat A floor designed tightly to the old density can be over-specified; one designed loosely may not cope if a tenant packs desks in.
Cat A as a landlord refurbishment
Most Cat A work is not on new buildings but on tired floors between lettings, when fan coils, lighting and ceilings reach the end of their life. It is also the moment to improve the EPC rating. Under the minimum energy efficiency standard a commercial landlord in England and Wales cannot grant a new lease on a building rated below E without a registered exemption, and the government has consulted on raising that bar. Swapping fluorescent fittings for LED with controls and replacing old plant are the measures that usually move a rating most.
Cat A reinstatement at the end of a lease
Many leases require the tenant to hand back the floor in Cat A condition. That means stripping out partitions, kitchens and tenant cabling, and reinstating ceilings, lighting and raised floor to a lettable standard. See dilapidations works for how that is priced and negotiated.
Where our information comes from
- British Council for Offices, Guide to Specification (2023)
- GOV.UK, Non-domestic private rented property: minimum energy efficiency standard, landlord guidance
- GOV.UK, Approved Document L: conservation of fuel and power
- HSE, HSG264 Asbestos: the survey guide
Cost ranges are typical figures from published UK cost guides and price guides, read November 2026, given before VAT. Firms that publish them are not named.
Floor area, the date the floor must be lettable and any survey you hold: that is enough to start.
Brief a contractorHow the work gets done
How a Cat A refurbishment of an existing floor normally runs.
Condition survey
Plant life, ceiling and floor condition, asbestos in the areas to be disturbed, EPC and fire strategy checked.
Specification
The Cat A standard written down: ceiling and lighting type, cooling system, floor void, toilets, and the density it is designed for.
Strip and rebuild
Strip-out, services first fix, raised floor and ceilings, plant installed, then finishes and decoration.
Commission and hand over
Air and water balancing, controls set up, fire alarm cause and effect tested, building control completion and O&M manuals.
Cat A questions
What is a Cat A fit-out?
How much does Cat A cost per m²?
What is the difference between Cat A and Cat B?
What is Cat A plus?
Who pays for Cat A?
Keep reading
- Cat B fit-out
The occupier's layer.
- Dilapidations works
Reinstating Cat A at lease end.
- M&E services
Heating, cooling, ventilation and power.
- Cost plan
Budget a Cat A floor by area and region.
Brief a contractor on a Cat A floor
Three short steps: where the building is, what the scope is, and who to speak to. Rough answers are fine; a contractor firms them up on a site visit.
Your brief stays with us until you approve the independent commercial refurbishment contractor we name for your building.
Received. This is what happens next.
- We find an independent commercial refurbishment contractor working in your part of the country on projects of this scale and sector, and contact you with the firm's name.
- Nothing goes to them until you say yes.
- Once you approve, the firm books a visit and follows up with a written proposal. You won't hear from us again unless you ask.